Wednesday, May 13, 2009

Roof Progress (week 6.5)

Here is the work that has been done in 1 week:



Thursday 5/7/09 ~ sheeted back wall on unit A









Friday 5/8/09 ~ sheeted end wall on unit B





Saturday 5/9/09 ~ sheeted front of garage and front of unit B (with the help of Jon, Kevin Henderson & Mike Boone)

See Geoffrey Wyatt's blog for pictures; he took some great pictures of everyone



Sunday 5/10/09 ~ Day of Rest (Mother's Day)




Monday 5/11/09 ~ sheeted back of garage and back of unit B ( with the help of Mike Boone & Bill Williams)






Tuesday 5/12/09 ~ tar papered back half of the roof




Wednesday 5/13/09 ~ tar papered front half of the roof